Construction Timeline
Closing Anticipated: April 29, 2020
Construction Commencement: By June 1, 2020
Demolition of the Robeson School: June – July 2020
PEPCO Duct Bank relocation along 10th Street: June - August, 2020
Appleton Completion: Expected August 2021
Substantial Completion: By April 2022
Final Completion: By May 2022
*More detail to be added as construction progresses.